Connecticut and New York

Dairy Renewable Natural Gas Projects

On-farm anaerobic digestion and gas upgrading

Oakridge, Marks, Lincoln, and Curtin are four projects built to turn dairy manure into renewable natural gas. Oakridge Dairy in Ellington, Connecticut, was the first farm in the SJI and REV LNG program to break ground. [1] [2]

Explore the four sites on the map

Oakridge Dairy from above, showing the round covered digester between the farm buildings and the manure storage lagoon
The round Oakridge digester sits between the dairy buildings and the covered storage lagoon.Connecticut GIS Office / CT ECO · Spring 2023 aerial imagery
Dairy projects featured
4 farms
Oakridge digester volume [1]
2M gallons
Oakridge announced facility investment [1]
$12M
Lincoln volume per digester [5]
2.2M gallons

Oakridge Dairy

Oakridge added a covered digester and gas-upgrading equipment to its manure-handling system. EnviTec reports that the upgraded gas is transported by trailer to a pipeline injection point. [3] [4]

How it fits the farm

Connecticut’s draft air permit describes two paths out of the digester. Biogas goes to the upgrading equipment, while the remaining material goes back to the farm for separation. The farm can reuse the solids as bedding and send the liquid to long-term storage. [3]

Oakridge project team

Host farm
Oakridge Dairy [1]
Project owner
South Jersey Industries (SJI) [4]
Development partner
REV LNG [1]
Digester equipment and gas upgrading
EnviTec Biogas USA [4]

My role

I worked as a construction project manager on all four dairy RNG projects.

Site locations

Oakridge Dairy · Ellington, CT

The round digester is visible between the barns and the covered storage lagoon. [3]

Marks Dairy · Martinsburg, NY

NYSEG identified REV LNG as the developer of the Marks Farms project in Lewis County. Its two covered tanks sit near the north end of the farm. [7]

Lincoln Dairy · Fleming, NY

Two 2.2-million-gallon digesters receive manure from nearby barns. EnviTec reports that the upgraded gas feeds directly into the local distribution system. [5]

Curtin Dairy · Cassville, NY

The Cassville facility upgrades biogas on site and sends the finished gas by trailer to a pipeline injection point. [4]

Project records

  1. SJI and REV LNG · Oakridge construction announcement

    Announced investment, digester volume, and project partners.

  2. SJI Renewable Energy Ventures · Dairy project portfolio

    Public project listings for Oakridge, Marks, Lincoln, and Curtin.

  3. Connecticut DEEP · Oakridge draft air permit

    Facility location, digester and gas-upgrading equipment, and material flows.

  4. EnviTec Biogas USA · Oakridge and Curtin

    Project locations, owner, development partner, and supplied equipment.

  5. EnviTec Biogas · Lincoln Dairy plant profile

    Digester sizes, gas upgrading, and the connection to the local gas grid.

  6. Procore · Marks Dairy construction profile

    Construction photograph and REV LNG’s account of the project.

  7. NYSEG · 2024–25 Winter Supply Plan

    Names Marks and Lincoln, identifies their towns, and describes the planned gas connections.

  8. Connecticut Geodata Portal · Spring 2023 aerial imagery

    Oakridge aerial imagery from the Connecticut GIS Office and CT ECO, released under CC0.

Software capture

World population · Estimated

A changing estimate of the people sharing this planet.

Archo interpolates between two United Nations World Population Prospects 2024 medium-variant projections:

The display spreads that projected change evenly across elapsed UTC time between those dates. It uses your device clock and updates once per second. It is a modeled illustration, not a live census or a count of observed births and deaths. Its individual digits do not represent measurement accuracy.

Reference date: 1 July 2026.

United Nations · World Population Prospects 2024 ↗
Source workbook · Medium variant · World · July population ↗

Source values converted from thousands to people. Retrieved 30 October 2026. CC BY 3.0 IGO; interpolation by Archo. No UN endorsement implied. Outside the two reference dates, the readout shows the nearest dated projection and stops updating. Reduced-motion preference starts the counter paused.